This article studies the speed-scaling robotic cell scheduling problem with constrained peak power consumption. The objective is to minimize cycle time and peak power consumption simultaneously. First, we formulate a bi-objective mixed integer programming model for the problem and propose a strategy to preprocess overlapping time windows. Then, we analyze the structural properties of the proposed model and develop an iterative "-constraint method to generate its complete Pareto front.