摘要
This paper addresses the single-track multi-hoist cyclic scheduling problem. In most existing studies, loaded hoist moves are implicitly or explicitly assumed to start and end within the same cycle. We give a counterexample to demonstrate that the optimal solution obtained with such an assumption is not necessarily the best one among all feasible solutions, called globally optimal solution. To obtain a globally optimal solution, we propose an improved mixed integer programming (MIP) approach for the multi-hoist cyclic scheduling problem with relaxation of the above assumption. Computational results on benchmark and randomly generated instances are reported and analyzed.
源语言 | 英语 |
---|---|
文章编号 | 6522200 |
页(从-至) | 302-309 |
页数 | 8 |
期刊 | IEEE Transactions on Automation Science and Engineering |
卷 | 11 |
期 | 1 |
DOI | |
出版状态 | 已出版 - 1月 2014 |