Multimode project scheduling based on particle swarm optimization

  • Hong Zhang
  • , C. M. Tam
  • , Heng Li
  • City University of Hong Kong
  • Hong Kong Polytechnic University

科研成果: 期刊稿件 › 文章 › 同行评审

114 引用 (Scopus)

摘要

The multimode resource-constrained projectscheduling problem (MRCPSP) considers both renewable and nonrenewable resources that have not been addressed efficiently in the construction field. This article introduces a methodology for solving the MRCPSP based on particle swarm optimization (PSO) that has not been utilized for this and other construction-related problems. The framework of the PSO-based methodology is developed. Aparticle representation formulation is proposed to represent the potential solution to the MRCPSP in terms of priority combination and mode combination for activities. Each particle-represented solution should be checked against the nonrenewable resource infeasibility and will be handled by adjusting the mode combination. The feasible particle-represented solution is transformed to a schedule through a serial generation scheme. Experimental analyses are presented to investigate the performance of the proposed methodology.

源语言英语
页(从-至)93-103
页数11
期刊Computer‐Aided Civil and Infrastructure Engineering
卷21
期2
DOI
出版状态已出版 - 2月 2006
已对外发布是

联合国可持续发展目标

此成果有助于实现下列可持续发展目标:

  1. 可持续发展目标 7 - 经济适用的清洁能源
    可持续发展目标 7 经济适用的清洁能源

引用此